Hey there!

Congratulations on ordering your Modal! We're super thrilled to help you through the installation process. We've prepared this installation guide to make it a piece of cake; from site work to final clean up, we've got you covered. It should have everything your General Contractor needs to know and answer all the questions you may have.

Keep in mind that each property is unique, so don't hesitate to reach out to our project manager if you come across any issues. We're here to make modular living a breeze for you!

how-it-works-hero

 

Install Guide

Hey there!

Congratulations on ordering your Modal! We're super thrilled to help you through the installation process. We've prepared this installation guide to make it a piece of cake; from site work to final clean up, we've got you covered. It should have everything your General Contractor needs to know and answer all the questions you may have.

Keep in mind that each property is unique, so don't hesitate to reach out to our project manager if you come across any issues. We're here to make modular living a breeze for you!

Site Prep  


    1. Coordinate inspections & permits with local jurisdiction for all site work (incl. utilities and foundation). Notify Modal of any required special inspections ASAP.

    2. Provide safety supplies, services and sanitation, dumpsters, and clean up/haul off

    3. Demo garages, sheds, trees, fences, etc. (if applicable)

    4. Install foundation (18” perimeter with crawl space, vapor barrier, utility sleeves through foundation)

    5. Run sewer, water, electrical, and data for the unit underground by connecting to the property’s existing utilities.

    6. Install 2x6 PT sill plate on the perimeter of the foundation. 

    7. Install Temp Power 

    8. Upgrade existing electrical meter on main home to support both Modal and main home (if applicable). Verify with the power company that no other upgrades are required. Apply for this permit as early as possible.

    9. Install septic tank system and leech field (if applicable)

    10. Run fire suppression water line from either the main water line or existing domestic line depending on jurisdiction requirements (if applicable)

Modal Site inspection/ Transport Unit

Placement

Supplies

  • 4” x ⅜” Tapcon Concrete Anchors

  • 6” x ⅜” Lag Bolts
  • Can of Marking Paint

  • Ramset Gun & Nails

  • Hammer Drill with Long ⅜” Masonry Bit

  • 9/16” Deep Socket & Wrench

  • Circular Saw

  • Sawzall

  • 2” x 6” Pressure Treated Sill Plate For The Perimeter of The Foundation
Number of Anchors Per Unit

4” x ⅜” Tapcon Concrete Anchors

Modal 00
Modal 01
Modal 02
12
16
20

 


Number of Bolts Per Unit

6” x ⅜” Lag Bolts

Modal 00
Modal 01
Modal 02
12
16
20

 

Instructions

  1. On the day of installation while the crane is setting up, install the sill plate to the perimeter of the foundation. Use the Ramset Gun to pin the sill plates to the foundation in a few places.

  2. Once the Modal arrives at the site, pull measurements off of the Modal for the bracket locations to make sure the floor joists are missed. Use these measurements to locate the brackets on the foundation, the brackets will sit behind the sill plate. Use marking paint to mark the bracket locations and drill holes for them. Once the holes are drilled, anchor the brackets to the foundation.

  3. When the truck driver pulls the chains that hold the Modal to the trailer, remove the D-rings from the Modal.

  4. Once the Modal is picked up by the crane, measurements will need to be taken of the strap locations. Based on those measurements, cut out 1’ from the sill plates centered on the strap locations. This allows the straps to be removed once the Modal is landed on the foundation and also provides ventilation to the crawl space.

  5. After the unit is landed, remove the 2x4 blocking that protects the base of the unit. Attach the screen mesh over the crawl space ventilation. To install the skirting, start at one corner, cut and bend a 90 on the left hand side of the first piece of skirting. Go counterclockwise, clicking the skirting together and attaching it with the supplied hardware.

Post-Install

  1. Confirm framing as-builts and install brackets prior to unit landing

  2. Secure Modal to foundation (see directions below)

  3. Install mesh/screen to cover vents for crawl space (see directions below)

  4. Install skirting around perimeter of foundation (Modal will provide skirting & hardware, simple process it clicks together) (see directions below)

  5. Mount condenser unit & mini-split head (if applicable)

  6. Provide and install line set cover

  7. Install gutters & downspout 

  8. Build deck to Modal (also add matching decking within the inset)

  9. Run electrical wire through conduit & make connection

  10. Water & sewer connection (one POC each)

  11. Commissioning

  12. Test all systems - hot/cold water at each sink and shower, proper drainage, all lights, etc.

  13. Run a dishwasher cycle to confirm proper operation/drainage

  14. Run a washer/dryer cycle to confirm proper operation/drainage, venting

  15. Test the range cooktop and oven

  16. Run the HVAC to ensure it heats and cools properly

  17. Install shower glass door (if applicable)

  18. Hang vanity mirror in bathroom

  19. Peel off protective cover from barn door (if applicable)

  20. Drywall/paint touch ups from any cracking during transport/install (Modal will provide paint for exterior and interior)

  21. Final grading around the unit to provide drainage away from the unit.

  22. Complete any other punch list items from homeowner or Modal

  23. Arrange final inspection & certificate of occupancy, send Modal final inspection report and C of O information